Silver House, Ghatkopar East
by Silver Infra Ventures Limited Liability Partnership · Ghatkopar East, Mumbai 400077 · Map
- Launched
- Jul 20254 yrs 5 mths promised
- Possession (MahaRERA)
- Dec 2029Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 43 of 13033% · 66 rehab units
- Buildings
- 10.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale43 booked out of 130 units
Rehab66 units for existing members
Total 196 units. Rehab units are not for sale.
Project facts
- Other units
- 196
- Total units
- 196
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 130
- Rehab units
- 66
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 97% | 0% | 0% | 43 | |
| 65% | 0% | 0% | 21 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Silver House by Silver Infra Ventures Limited Liability Partnership is a 196-unit SRA-sanctioned project in Ghatkopar East, Mumbai 400077, launched in July 2025 with possession due in December 2029. 43 units booked out of 130 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Silver House is an SRA-sanctioned project by Silver Infra Ventures Limited Liability Partnership in Ghatkopar East, Mumbai 400077, registered with MahaRERA as PC1180002500363. It was launched in July 2025. It has 196 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 196 units, 130 are for sale and 66 are rehab units for existing members.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation 97% complete, structure (RCC) not started, final finishes not started.
43 units booked out of 130 units for sale (33%). Since the July 2026 update, 22 more units have been booked.