Sixty 3 W.E. Bizpark, Goregaon East

by Agm Vijaylaxmi Elite LLP · Goregaon East, Mumbai 400063 · Map

Launched
Sep 20255 yrs 9 mths promised
Possession (MahaRERA)
Jun 2031Not extended
Concrete structure
26%Mid-construction
Booked
2 of 972% · 0 in Jul 2026
Buildings
11.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
97
Total units
97
Buildings
1
Land
1.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)26%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 11%Oct 2026: Concrete structure (RCC) 26%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 26%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%26%0%2
100%11%0%0
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Sixty 3 W.E. Bizpark by Agm Vijaylaxmi Elite LLP is a 97-unit SRA-sanctioned project in Goregaon East, Mumbai 400063, launched in September 2025 with possession due in June 2031. 2 units booked out of total 97 units. The concrete structure (RCC) is 26% complete.

Read full summary

Sixty 3 W.E. Bizpark is an SRA-sanctioned project by Agm Vijaylaxmi Elite LLP in Goregaon East, Mumbai 400063, registered with MahaRERA as PC1180002500686. It was launched in September 2025. It has 97 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2031, unchanged since launch. Construction: excavation complete, structure (RCC) 26% complete, final finishes not started.

2 units booked out of total 97 units (2%). Since the July 2026 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 11% to 26%.