Crescent Wtc T2 Phase II, Chandivali

by Crown Realty Developers Private Limited · Chandivali, Mumbai 400072 · Map

Launched
Sep 20252 yrs 11 mths promised
Possession (MahaRERA)
Aug 2028Not extended
Concrete structure
35%Mid-construction
Booked
32 of 6648%
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
66
Total units
66
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)35%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 35%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 35%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%35%0%32
100%0%0%32
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Crescent Wtc T2 Phase II by Crown Realty Developers Private Limited is a 66-unit BMC-sanctioned project in Chandivali, Mumbai 400072, launched in September 2025 with possession due in August 2028. 32 units booked out of total 66 units. The concrete structure (RCC) is 35% complete.

Read full summary

Crescent Wtc T2 Phase II is a BMC-sanctioned project by Crown Realty Developers Private Limited in Chandivali, Mumbai 400072, registered with MahaRERA as PC1180002500950. It was launched in September 2025. It has 66 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is August 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 35% complete, final finishes not started.

32 units booked out of total 66 units (48%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 35%.