Notan Edge, Vile Parle West

by Notan Empress Private Limited · Vile Parle West, Mumbai 400056 · Map

Launched
Sep 20253 yrs 3 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
0%Early stage
Booked
1 of 1100%
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
1
Total units
1
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 40%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%1
100%0%0%1
40%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Notan Edge by Notan Empress Private Limited is a 1-unit BMC-sanctioned project in Vile Parle West, Mumbai 400056, launched in September 2025 with possession due in December 2028. 1 unit booked out of total 1 unit. Work on the concrete structure (RCC) has not started.

Read full summary

Notan Edge is a BMC-sanctioned project by Notan Empress Private Limited in Vile Parle West, Mumbai 400056, registered with MahaRERA as PC1180002500970. It was launched in September 2025. It has 1 unit in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

1 unit booked out of total 1 unit (100%).