Harisharan Tattvaa, Mulund West

by Ashapura Reality Private Limited · Mulund West, Mumbai 400080 · Map

Launched
Nov 20254 yrs 4 mths promised
Possession (MahaRERA)
Mar 2030Not extended
Concrete structure
38%Mid-construction
Booked (free sale)
4 of 2020% · 5 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale4 booked out of 20 units

Rehab5 units for existing members

Total 25 units. Rehab units are not for sale.

Project facts

Other units
25
Total units
25
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
20
Rehab units
5

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)38%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 95%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 15%Oct 2026: Concrete structure (RCC) 38%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 38%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%38%0%4
100%15%0%4
95%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Harisharan Tattvaa by Ashapura Reality Private Limited is a 25-unit SRA-sanctioned project in Mulund West, Mumbai 400080, launched in November 2025 with possession due in March 2030. 4 units booked out of 20 units for sale. The concrete structure (RCC) is 38% complete.

Read full summary

Harisharan Tattvaa is an SRA-sanctioned project by Ashapura Reality Private Limited in Mulund West, Mumbai 400080, registered with MahaRERA as PC1180002501531. It was launched in November 2025. It has 25 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 25 units, 20 are for sale and 5 are rehab units for existing members.

Its registered possession date is March 2030, unchanged since launch. Construction: excavation complete, structure (RCC) 38% complete, final finishes not started.

4 units booked out of 20 units for sale (20%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 15% to 38%.