JP Commerz, Kandivali West

by Metallica Industries Limited · Kandivali West, Mumbai 400067 · Map

Launched
Feb 20263 yrs 10 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
90%Mid-construction
Booked (free sale)
125 of 16974% · 351 rehab units
Buildings
11.8 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale125 booked out of 169 units

Rehab351 units for existing members

Total 520 units. Rehab units are not for sale.

Project facts

Other units
520
Total units
520
Buildings
1
Land
1.8 acres
Phases
1
MahaRERA complaints
1
Free-sale units
169
Rehab units
351

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)90%
Finishes, lifts and services10%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 96%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 85%Oct 2026: Concrete structure (RCC) 90%Jul 2026: Final finishes 10%Oct 2026: Final finishes 10%Excavation 100%Concrete structure (RCC) 90%Final finishes 10%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%10%125
96%85%10%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

JP Commerz by Metallica Industries Limited is a 520-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in February 2026 with possession due in December 2029. 125 units booked out of 169 units for sale. The concrete structure (RCC) is 90% complete.

Read full summary

JP Commerz is a BMC-sanctioned project by Metallica Industries Limited in Kandivali West, Mumbai 400067, registered with MahaRERA as PC1180002502439. It was launched in February 2026. It has 520 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 520 units, 169 are for sale and 351 are rehab units for existing members.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 90% complete, final finishes 10% complete.

125 units booked out of 169 units for sale (74%). Since the July 2026 update, 125 more units have been booked and the reported concrete structure (RCC) has gone from 85% to 90%.