DRM Sheetal Landmark, Goregaon West

by Drm Lifespace LLP · Goregaon West, Mumbai 400104 · Map

Launched
Sep 20263 yrs 3 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
0 of 60% · 3 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 6 units

Rehab3 units for existing members

Total 9 units. Rehab units are not for sale.

Project facts

Other units
9
Total units
9
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
6
Rehab units
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

DRM Sheetal Landmark by Drm Lifespace LLP is a 9-unit BMC-sanctioned project in Goregaon West, Mumbai 400104, launched in September 2026 with possession due in December 2029. 0 units booked out of 6 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

DRM Sheetal Landmark is a BMC-sanctioned project by Drm Lifespace LLP in Goregaon West, Mumbai 400104, registered with MahaRERA as PC1180002601762. It was launched in September 2026. It has 9 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 9 units, 6 are for sale and 3 are rehab units for existing members.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.

0 units booked out of 6 units for sale (0%).