Kush Icon, Malad West

by Kush Realcon LLP · Malad West, Mumbai 400064 · Map

Launched
Oct 20262 yrs 11 mths promised
Possession (MahaRERA)
Sep 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
0 of 100% · 19 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 10 units

Rehab19 units for existing members

Total 29 units. Rehab units are not for sale.

Project facts

Other units
29
Total units
29
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
10
Rehab units
19

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Kush Icon by Kush Realcon LLP is a 29-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in October 2026 with possession due in September 2029. 0 units booked out of 10 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Kush Icon is a BMC-sanctioned project by Kush Realcon LLP in Malad West, Mumbai 400064, registered with MahaRERA as PC1180002602227. It was launched in October 2026. It has 29 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 29 units, 10 are for sale and 19 are rehab units for existing members.

Its registered possession date is September 2029, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.

0 units booked out of 10 units for sale (0%).