io Tower by PCPL, Goregaon West
by Pranav Constructions Limited · Goregaon West, Mumbai 400104 · Map
- Launched
- Sep 20264 yrs 5 mths promised
- Possession (MahaRERA)
- Feb 2031Not extended
- Concrete structure
- 0%Early stage
- Booked
- 3 of 2612%
- Buildings
- 11 acre
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 26
- Total units
- 26
- Buildings
- 1
- Land
- 1 acre
- Phases
- 1
- MahaRERA complaints
- 0
- Reserved units
- 3
Construction progress
As reported by the builder to MahaRERA (whole project)
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | 3 |
"–" means MahaRERA shows no figure for that update.
About this project
io Tower by PCPL by Pranav Constructions Limited is a 26-unit MMRDA-sanctioned project in Goregaon West, Mumbai 400104, launched in September 2026 with possession due in February 2031. 3 units booked out of total 26 units. Work on the concrete structure (RCC) has not started.
Read full summary
io Tower by PCPL is an MMRDA-sanctioned project by Pranav Constructions Limited in Goregaon West, Mumbai 400104, registered with MahaRERA as PC1181012601793. It was launched in September 2026. It has 26 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is February 2031, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.
3 units booked out of total 26 units (12%).
Pranav's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 47 |
|---|---|
| Total units across these projects | 2,365 |
| Completed without extending the possession date | 24 |
| Completed after an extension | 0 |
| Lapsed | 0 |
| Under construction | 23 |
| Possession date extended on the builder's application | 0 |
| Typical time from launch to 100% structure | 2 years 10 months |
| MahaRERA complaints (filed by or against the builder), all Pranav projects | 4 (4 of 47 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.