Farida Heights, Mandvi

by Ideal Life Spaces LLP · Mandvi, Mumbai 400003 · Map

Launched
Sep 20251 yr 3 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
3 of 3110% · 47 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale3 booked out of 31 units

Rehab47 units for existing members

Land-owner share6 units, not for sale

Total 84 units. Rehab and land-owner units are not for sale.

Project facts

1 BHK
73
Other units
11
Total units
84
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
31
Rehab units
47
Land-owner share (not for sale)
6

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 40%Jul 2026: Concrete structure (RCC) 90%Oct 2026: Concrete structure (RCC) 100%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%3
100%90%0%3
100%40%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400003

Projects with 30–150 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400003
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 3 mths4 yrs 8 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Dec 2026Dec 2030
Concrete structure (RCC)100%25%
Units booked (free sale)10%0%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Farida Heights by Ideal Life Spaces LLP is an 84-unit BMC-sanctioned project in Mandvi, Mumbai 400003, launched in September 2025 with possession due in December 2026. 3 units booked out of 31 units for sale. The concrete structure (RCC) is complete.

Read full summary

Farida Heights is a BMC-sanctioned project by Ideal Life Spaces LLP in Mandvi, Mumbai 400003, registered with MahaRERA as PM1170002500991. It was launched in September 2025. It has 84 units in 1 building: 73 homes (1 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 84 units, 31 are for sale, 47 are rehab units for existing members and 6 are the land-owner's share, not for sale.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.

3 units booked out of 31 units for sale (10%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 90% to 100%.