Nirban Nestlings, Mahalaxmi
by Nirban Infrastructure Pvt Ltd · Mahalaxmi, Mumbai 400011 · Map
- Launched
- Nov 20254 yrs 1 mth promised
- Possession (MahaRERA)
- Dec 2029Not extended
- Concrete structure
- 22%Mid-construction
- Booked (free sale)
- 5 of 4212% · 69 rehab units
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale5 booked out of 42 units
Rehab69 units for existing members
Total 111 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 11
- 2 BHK
- 18
- 3 BHK
- 2
- Other units
- 80
- Total units
- 111
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 42
- Rehab units
- 69
- Reserved units
- 5
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 22% | 0% | 5 | |
| 100% | 10% | 0% | 5 | |
| 80% | 0% | 0% | 1 |
"–" means MahaRERA shows no figure for that update.
About this project
Nirban Nestlings by Nirban Infrastructure Pvt Ltd is a 111-unit BMC-sanctioned project in Mahalaxmi, Mumbai 400011, launched in November 2025 with possession due in December 2029. 5 units booked out of 42 units for sale. The concrete structure (RCC) is 22% complete.
Read full summary
Nirban Nestlings is a BMC-sanctioned project by Nirban Infrastructure Pvt Ltd in Mahalaxmi, Mumbai 400011, registered with MahaRERA as PM1170002501575. It was launched in November 2025. It has 111 units in 1 building: 31 homes (1, 2 and 3 BHK) and 80 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 111 units, 42 are for sale and 69 are rehab units for existing members.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 22% complete, final finishes not started.
5 units booked out of 42 units for sale (12%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 10% to 22%.