Sattva Sumera, Parel

by Alperton Developers And Contractors Private Limited · Parel, Mumbai 400012 · Map

Launched
Mar 20265 yrs 9 mths promised
Possession (MahaRERA)
Dec 2031Not extended
Concrete structure
0%Early stage
Booked
63 of 50912% · 21 in Jul 2026
Buildings
119.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
335
3 BHK
164
Other units
10
Total units
509
Buildings
1
Land
19.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 85%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%63
85%0%0%21

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Sattva Sumera by Alperton Developers And Contractors Private Limited is a 509-unit SRA-sanctioned project in Parel, Mumbai 400012, launched in March 2026 with possession due in December 2031. 63 units booked out of total 509 units. Work on the concrete structure (RCC) has not started.

Read full summary

Sattva Sumera is an SRA-sanctioned project by Alperton Developers And Contractors Private Limited in Parel, Mumbai 400012, registered with MahaRERA as PM1170002502568. It was launched in March 2026. It has 509 units in 1 building: 499 homes (2 and 3 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2031, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

63 units booked out of total 509 units (12%). Since the July 2026 update, 42 more units have been booked.