Presidence Marina, Mazgaon
by Futuristic Realty · Mazgaon, Mumbai 400010 · Map
- Launched
- Mar 20262 yrs 9 mths originally promised
- Possession (MahaRERA)
- Dec 2030Extended by 2 yrs
- Concrete structure
- 0%Early stage
- Booked
- 1 of 264%
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 6
- 2 BHK
- 7
- 3 BHK
- 1
- Other units
- 12
- Total units
- 26
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Reserved units
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Work not started as of Oct 2026
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | 1 | |
| 0% | 0% | 0% | 1 |
"–" means MahaRERA shows no figure for that update.
About this project
Presidence Marina by Futuristic Realty is a 26-unit BMC-sanctioned project in Mazgaon, Mumbai 400010, launched in March 2026 with possession due in December 2030. 1 unit booked out of total 26 units. Work on the concrete structure (RCC) has not started.
Read full summary
Presidence Marina is a BMC-sanctioned project by Futuristic Realty in Mazgaon, Mumbai 400010, registered with MahaRERA as PM1170002502709. It was launched in March 2026. It has 26 units in 1 building: 14 homes (1, 2 and 3 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2030, extended by 2 years from the original December 2028. Construction: excavation not started, structure (RCC) not started, final finishes not started.
1 unit booked out of total 26 units (4%).