Skip to main content

Dhuleva One50, Grant Road

by The New Era Agencies Pvt Ltd · Grant Road, Mumbai 400007 · Map

Launched
Mar 20267 yrs 9 mths promised
Possession (MahaRERA)
Dec 2033Not extended
Concrete structure
0%Early stage
Booked (free sale)
1 of 119% · 37 rehab units
Buildings
20.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale1 booked out of 11 units

Rehab37 units for existing members

Total 48 units. Rehab units are not for sale.

Project facts

2 BHK
3
3 BHK
15
4 BHK
4
5+ BHK
24
Other units
2
Total units
48
Buildings
2
Land
0.7 acres
Phases
1
MahaRERA complaints
0
Free-sale units
11
Rehab units
37

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation8%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 1%Oct 2026: Excavation 8%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 8%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
8%0%0%1
1%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Dhuleva One50 by The New Era Agencies Pvt Ltd is a 48-unit BMC-sanctioned project in Grant Road, Mumbai 400007, launched in March 2026 with possession due in December 2033. 1 unit booked out of 11 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Dhuleva One50 is a BMC-sanctioned project by The New Era Agencies Pvt Ltd in Grant Road, Mumbai 400007, registered with MahaRERA as PM1170002502807. It was launched in March 2026. It has 48 units in 2 buildings: 46 homes (2, 3, 4 and 5+ BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 48 units, 11 are for sale and 37 are rehab units for existing members.

Its registered possession date is December 2033, unchanged since launch. Construction: excavation 8% complete, structure (RCC) not started, final finishes not started.

1 unit booked out of 11 units for sale (9%). Since the July 2026 update, 1 more unit has been booked.