One Parel, Parel

by Aztec Developers · Parel, Mumbai 400012 · Map

Launched
Jun 20264 yrs 6 mths promised
Possession (MahaRERA)
Dec 2030Not extended
Concrete structure
0%Early stage
Booked (free sale)
20 of 4643% · 39 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale20 booked out of 46 units

Rehab39 units for existing members

Total 85 units. Rehab units are not for sale.

Project facts

1 BHK
73
2 BHK
6
Other units
6
Total units
85
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
46
Rehab units
39

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Work not started as of Oct 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%20
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

One Parel by Aztec Developers is an 85-unit BMC-sanctioned project in Parel, Mumbai 400012, launched in June 2026 with possession due in December 2030. 20 units booked out of 46 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

One Parel is a BMC-sanctioned project by Aztec Developers in Parel, Mumbai 400012, registered with MahaRERA as PM1171012600682. It was launched in June 2026. It has 85 units in 1 building: 79 homes (1 and 2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 85 units, 46 are for sale and 39 are rehab units for existing members.

Its registered possession date is December 2030, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.

20 units booked out of 46 units for sale (43%). Since the July 2026 update, 20 more units have been booked.