Advent Neel Residency, Bhandup West

by Neel Realtors · Bhandup West, Mumbai 400078 · Map

Launched
Oct 20244 yrs 2 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
40%Mid-construction
Booked (free sale)
23 of 3664% · 10 rehab units
Buildings
30.8 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale23 booked out of 36 units

Rehab10 units for existing members

Total 46 units. Rehab units are not for sale.

Project facts

1 BHK
16
2 BHK
19
Other units
11
Total units
46
Buildings
3
Land
0.8 acres
Phases
1
MahaRERA complaints
0
Free-sale units
36
Rehab units
10

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)40%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 12%Jul 2026: Excavation 12%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 40%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 40%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%40%0%23
12%0%0%2
12%0%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400078

Projects with 10–70 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400078
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 2 mths2 yrs 7 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)Dec 2028Jan 2027
Concrete structure (RCC)40%6%
Units booked (free sale)64%55%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Advent Neel Residency by Neel Realtors is a 46-unit BMC-sanctioned project in Bhandup West, Mumbai 400078, launched in October 2024 with possession due in December 2028. 23 units booked out of 36 units for sale. The concrete structure (RCC) is 40% complete.

Read full summary

Advent Neel Residency is a BMC-sanctioned project by Neel Realtors in Bhandup West, Mumbai 400078, registered with MahaRERA as PM1180002400062. It was launched in October 2024. It has 46 units in 3 buildings: 35 homes (1 and 2 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 46 units, 36 are for sale and 10 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 40% complete, final finishes not started.

23 units booked out of 36 units for sale (64%). Since the July 2026 update, 21 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 40%.