Megh Mahal Chsl, Borivali East
by Samarpan Homes & Developers · Borivali East, Mumbai 400066 · Map
- Launched
- Jul 20252 yrs 5 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 70%Mid-construction
- Booked (free sale)
- 0 of 220% · 3 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 22 units
Rehab3 units for existing members
Total 25 units. Rehab units are not for sale.
Project facts
- 1 RK
- 1
- 1 BHK
- 2
- 2 BHK
- 1
- Other units
- 21
- Total units
- 25
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 22
- Rehab units
- 3
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 70% | 0% | 0 | |
| 100% | 50% | 0% | 0 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Megh Mahal Chsl by Samarpan Homes & Developers is a 25-unit BMC-sanctioned project in Borivali East, Mumbai 400066, launched in July 2025 with possession due in December 2027. 0 units booked out of 22 units for sale. The concrete structure (RCC) is 70% complete.
Read full summary
Megh Mahal Chsl is a BMC-sanctioned project by Samarpan Homes & Developers in Borivali East, Mumbai 400066, registered with MahaRERA as PM1180002500265. It was launched in July 2025. It has 25 units in 1 building: 4 homes (1 RK, 1 BHK and 2 BHK) and 21 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 25 units, 22 are for sale and 3 are rehab units for existing members.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 70% complete, final finishes not started.
0 units booked out of 22 units for sale (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 50% to 70%.