Monarch Majestic, Andheri East

by New Monarch Builders And Contractors · Andheri East, Mumbai 400059 · Map

Launched
Aug 20253 yrs 3 mths promised
Possession (MahaRERA)
Nov 2028Not extended
Concrete structure
0%Early stage
Booked
48 of 17927% · 31 in Jul 2026
Buildings
26.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
16
1 BHK
156
2 BHK
1
Other units
6
Total units
179
Buildings
2
Land
6.6 acres
Phases
1
MahaRERA complaints
0
Reserved units
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation90%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 8%Jul 2026: Excavation 40%Oct 2026: Excavation 90%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 90%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
90%0%0%48
40%0%0%31
8%0%0%5

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Monarch Majestic by New Monarch Builders And Contractors is a 179-unit SRA-sanctioned project in Andheri East, Mumbai 400059, launched in August 2025 with possession due in November 2028. 48 units booked out of total 179 units. Work on the concrete structure (RCC) has not started.

Read full summary

Monarch Majestic is an SRA-sanctioned project by New Monarch Builders And Contractors in Andheri East, Mumbai 400059, registered with MahaRERA as PM1180002500557. It was launched in August 2025. It has 179 units in 2 buildings: 173 homes (1 RK, 1 BHK and 2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is November 2028, unchanged since launch. Construction: excavation 90% complete, structure (RCC) not started, final finishes not started.

48 units booked out of total 179 units (27%). Since the July 2026 update, 17 more units have been booked.