Malad Vrindavan CHSL, Malad West
by Omnetra DB Infra LLP · Malad West, Mumbai 400064 · Map
- Launched
- Aug 20253 yrs 4 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 3 of 2015% · 38 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale3 booked out of 20 units
Rehab38 units for existing members
Total 58 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 9
- 2 BHK
- 28
- 3 BHK
- 9
- Other units
- 12
- Total units
- 58
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 20
- Rehab units
- 38
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 3 | |
| 100% | 0% | 0% | 4 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400064
Projects with 20–100 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 4 mths | 2 yrs 10 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2028 | Jun 2028 |
| Concrete structure (RCC) | 0% | 42% |
| Units booked (free sale) | 15% | 10% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Justin Co-Op. Hsg. Soc. Ltd, Malad West
- Rishabraj Ceramont, Malad West
- Annapurna Sadan CHS LTD, Malad West
- Metro Majestic, Malad West
- The Redevelopment of Shree Santoshi Nagar CHSL, Malad West
- Sahakar Shanti Signature, Malad West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Justin Co-Op. Hsg. Soc. Ltd | September 2025 | March 2029 | 50% | 4 units booked out of 23 units for sale |
| Rishabraj Ceramont | July 2025 | December 2031 | 40% | 1 unit booked out of 18 units for sale |
| Annapurna Sadan CHS LTD | July 2025 | May 2028 | 100% | 3 units booked out of 22 units for sale |
| Metro Majestic | July 2025 | December 2027 | 45% | 7 units booked out of 16 units for sale |
| The Redevelopment of Shree Santoshi Nagar CHSL | July 2025 | June 2028 | 0% | 0 units booked out of 20 units for sale |
| Sahakar Shanti Signature | October 2025 | June 2028 | 7% | 1 unit booked out of 16 units for sale |
About this project
Malad Vrindavan CHSL by Omnetra DB Infra LLP is a 58-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in August 2025 with possession due in December 2028. 3 units booked out of 20 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Malad Vrindavan CHSL is a BMC-sanctioned project by Omnetra DB Infra LLP in Malad West, Mumbai 400064, registered with MahaRERA as PM1180002500621. It was launched in August 2025. It has 58 units in 1 building: 46 homes (1, 2 and 3 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 58 units, 20 are for sale and 38 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.
3 units booked out of 20 units for sale (15%).