Aviara, Santacruz West

by Baluwala Builders · Santacruz West, Mumbai 400054 · Map

Launched
Aug 20256 yrs 4 mths promised
Possession (MahaRERA)
Dec 2031Not extended
Concrete structure
0%Early stage
Booked
212 of 26879% · 201 in Jul 2026
Buildings
20.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
226
2 BHK
27
3 BHK
8
Other units
7
Total units
268
Buildings
2
Land
0.7 acres
Phases
1
MahaRERA complaints
0
Reserved units
148

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 95%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%212
95%0%0%201
0%0%0%183

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Aviara by Baluwala Builders is a 268-unit SRA-sanctioned project in Santacruz West, Mumbai 400054, launched in August 2025 with possession due in December 2031. 212 units booked out of total 268 units. Work on the concrete structure (RCC) has not started.

Read full summary

Aviara is an SRA-sanctioned project by Baluwala Builders in Santacruz West, Mumbai 400054, registered with MahaRERA as PM1180002500664. It was launched in August 2025. It has 268 units in 2 buildings: 261 homes (1, 2 and 3 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2031, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

212 units booked out of total 268 units (79%). Since the July 2026 update, 11 more units have been booked.