Skip to main content

Ace Marvel, Mulund West

by Ace properties · Mulund West, Mumbai 400080 · Map

Launched
Sep 20253 yrs 3 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
35%Mid-construction
Booked (free sale)
2 of 287% · 37 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale2 booked out of 28 units

Rehab37 units for existing members

Total 65 units. Rehab units are not for sale.

Project facts

1 RK
1
1 BHK
16
2 BHK
42
3 BHK
1
Other units
5
Total units
65
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
28
Rehab units
37

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)35%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 5%Jul 2026: Concrete structure (RCC) 5%Oct 2026: Concrete structure (RCC) 35%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 35%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%35%0%2
100%5%0%1
100%5%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400080

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 3 mths3 yrs 1 mth
Possession date extendedNo1 of 6
Possession date (MahaRERA)Dec 2028Jun 2029
Concrete structure (RCC)35%22%
Units booked (free sale)7%51%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Ace Marvel by Ace properties is a 65-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in September 2025 with possession due in December 2028. 2 units booked out of 28 units for sale. The concrete structure (RCC) is 35% complete.

Read full summary

Ace Marvel is a BMC-sanctioned project by Ace properties in Mulund West, Mumbai 400080, registered with MahaRERA as PM1180002500766. It was launched in September 2025. It has 65 units in 1 building: 60 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 65 units, 28 are for sale and 37 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 35% complete, final finishes not started.

2 units booked out of 28 units for sale (7%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 5% to 35%.