Rishabraj Forest Front, Borivali East
by Rishabraj Estate Developers Pvt Ltd · Borivali East, Mumbai 400066 · Map
- Launched
- Oct 20253 yrs 2 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 70%Mid-construction
- Booked (free sale)
- 1 of 812% · 23 rehab units
- Buildings
- 30.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale1 booked out of 8 units
Rehab23 units for existing members
Total 31 units. Rehab units are not for sale.
Project facts
- 1 RK
- 2
- 1 BHK
- 4
- 2 BHK
- 17
- 3 BHK
- 4
- Other units
- 4
- Total units
- 31
- Buildings
- 3
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 8
- Rehab units
- 23
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 70% | 0% | 1 | |
| 100% | 10% | 0% | 0 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400066
Projects with 10–60 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 2 mths | 2 yrs 11 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2028 | Sep 2028 |
| Concrete structure (RCC) | 70% | 65% |
| Units booked (free sale) | 12% | 27% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Parekh Eminence, Borivali East
- Rijin Pride, Borivali East
- Tasmai Ananda, Borivali East
- 66 Infinia, Borivali East
- Shreenath Regency, Borivali East
- Parshuram Heights, Borivali East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Parekh Eminence | October 2025 | December 2028 | 0% | 3 units booked out of 15 units for sale |
| Rijin Pride | November 2025 | September 2028 | 0% | 0 units booked out of 13 units for sale |
| Tasmai Ananda | August 2025 | June 2027 | 60% | 6 units booked out of 12 units for sale |
| 66 Infinia | December 2025 | December 2028 | 70% | 10 units booked out of 20 units for sale |
| Shreenath Regency | August 2025 | October 2027 | 70% | 1 unit booked out of 3 units for sale |
| Parshuram Heights | August 2025 | September 2028 | 80% | 1 unit booked out of 32 units for sale |
About this project
Rishabraj Forest Front by Rishabraj Estate Developers Pvt Ltd is a 31-unit BMC-sanctioned project in Borivali East, Mumbai 400066, launched in October 2025 with possession due in December 2028. 1 unit booked out of 8 units for sale. The concrete structure (RCC) is 70% complete.
Read full summary
Rishabraj Forest Front is a BMC-sanctioned project by Rishabraj Estate Developers Pvt Ltd in Borivali East, Mumbai 400066, registered with MahaRERA as PM1180002501049. It was launched in October 2025. It has 31 units in 3 buildings: 27 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 31 units, 8 are for sale and 23 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 70% complete, final finishes not started.
1 unit booked out of 8 units for sale (12%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 10% to 70%.
Rishabraj's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 43 |
|---|---|
| Total units across these projects | 1,514 |
| Completed without extending the possession date | 22 |
| Completed after an extension | 3 |
| Lapsed | 3 |
| Under construction | 15 |
| Possession date extended on the builder's application | 4 |
| Typical time from launch to 100% structure | 2 years 9 months |
| MahaRERA complaints (filed by or against the builder), all Rishabraj projects | 33 (4 of 43 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.