Skip to main content

Gold Leaf, Borivali West

by Shelaji Horizon LLP · Borivali West, Mumbai 400092 · Map

Launched
Oct 20254 yrs 2 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
4%Mid-construction
Booked (free sale)
11 of 2055% · 83 rehab units
Buildings
10.9 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale11 booked out of 20 units

Rehab83 units for existing members

Total 103 units. Rehab units are not for sale.

Project facts

1 BHK
1
2 BHK
38
3 BHK
53
Other units
11
Total units
103
Buildings
1
Land
0.9 acres
Phases
1
MahaRERA complaints
0
Free-sale units
20
Rehab units
83

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)4%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 4%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 4%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%4%0%11
100%0%0%2
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400092

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400092
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 2 mths4 yrs 2 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2029Dec 2029
Concrete structure (RCC)4%6%
Units booked (free sale)55%3%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Gold Leaf by Shelaji Horizon LLP is a 103-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in October 2025 with possession due in December 2029. 11 units booked out of 20 units for sale. The concrete structure (RCC) is 4% complete.

Read full summary

Gold Leaf is a BMC-sanctioned project by Shelaji Horizon LLP in Borivali West, Mumbai 400092, registered with MahaRERA as PM1180002501101. It was launched in October 2025. It has 103 units in 1 building: 92 homes (1, 2 and 3 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 103 units, 20 are for sale and 83 are rehab units for existing members.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 4% complete, final finishes not started.

11 units booked out of 20 units for sale (55%). Since the July 2026 update, 9 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 4%.