Gala Ares, Mulund West
by Square One Realty · Mulund West, Mumbai 400080 · Map
- Launched
- Nov 20254 yrs 1 mth promised
- Possession (MahaRERA)
- Dec 2029Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 0 of 20% · 18 rehab units
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 2 units
Rehab18 units for existing members
Total 20 units. Rehab units are not for sale.
Project facts
- Other units
- 20
- Total units
- 20
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 2
- Rehab units
- 18
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 0 | |
| 100% | 0% | 0% | 0 | |
| 20% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Gala Ares by Square One Realty is a 20-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in November 2025 with possession due in December 2029. 0 units booked out of 2 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Gala Ares is a BMC-sanctioned project by Square One Realty in Mulund West, Mumbai 400080, registered with MahaRERA as PM1180002501625. It was launched in November 2025. It has 20 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 20 units, 2 are for sale and 18 are rehab units for existing members.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.
0 units booked out of 2 units for sale (0%).