Aniket, Dahisar
by Shree Magnus Construction · Dahisar, Mumbai 400068 · Map
- Launched
- Dec 20253 yrs promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 0 of 60% · 14 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 6 units
Rehab14 units for existing members
Total 20 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 10
- Other units
- 10
- Total units
- 20
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 6
- Rehab units
- 14
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Work not started as of Oct 2026
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | 0 | |
| 0% | 0% | 0% | 0 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400068
Projects with up to 20 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs | 2 yrs 9 mths |
| Possession date extended | No | 1 of 3 |
| Possession date (MahaRERA) | Dec 2028 | Aug 2028 |
| Concrete structure (RCC) | 0% | 0% |
| Units booked (free sale) | 0% | 0% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Mv Dahisar Bhavana, Dahisar
- RL Sadguru, Dahisar
- Vasant Villa, Dahisar
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Mv Dahisar Bhavana | November 2025 | May 2029 | 5% | 4 units booked out of 22 units for sale |
| RL Sadguru | September 2025 | June 2028 | 0% | 0 units booked out of 9 units for sale |
| Vasant Villa | July 2026 | August 2028 | 0% | 0 units booked out of 10 units for sale |
About this project
Aniket by Shree Magnus Construction is a 20-unit BMC-sanctioned project in Dahisar, Mumbai 400068, launched in December 2025 with possession due in December 2028. 0 units booked out of 6 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Aniket is a BMC-sanctioned project by Shree Magnus Construction in Dahisar, Mumbai 400068, registered with MahaRERA as PM1180002501643. It was launched in December 2025. It has 20 units in 1 building: 10 homes (2 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 20 units, 6 are for sale and 14 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.
0 units booked out of 6 units for sale (0%).