45th Marine, Juhu
by Ummang Harmony Lifestyles LLP · Juhu, Mumbai 400049 · Map
- Launched
- Dec 20254 yrs 6 mths promised
- Possession (MahaRERA)
- Jun 2030Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 53 of 5695% · 32 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale53 booked out of 56 units
Rehab32 units for existing members
Total 88 units. Rehab units are not for sale.
Project facts
- 1 RK
- 50
- 2 BHK
- 11
- 3 BHK
- 13
- 4 BHK
- 7
- Other units
- 7
- Total units
- 88
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 56
- Rehab units
- 32
- Reserved units
- 50
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 45% | 0% | 0% | 53 | |
| 30% | 0% | 0% | 53 | |
| 0% | 0% | 0% | 50 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400049
Projects with 40–200 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 6 mths | 3 yrs 10 mths |
| Possession date extended | No | 0 of 4 |
| Possession date (MahaRERA) | Jun 2030 | Sep 2029 |
| Concrete structure (RCC) | 0% | 0% |
| Units booked (free sale) | 95% | 26% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Vaswani Seascape, Juhu
- Helios Apartments, Juhu
- Viraasat, Juhu
- Spectrum Life, Juhu
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Vaswani Seascape | February 2026 | December 2028 | 0% | 1 unit booked out of 6 units for sale |
| Helios Apartments | February 2026 | June 2030 | 0% | 31 units booked out of 41 units for sale |
| Viraasat | September 2026 | June 2030 | 0% | 0 units booked out of 19 units for sale |
| Spectrum Life | January 2025 | December 2028 | 15% | 14 units booked out of 40 units for sale |
About this project
45th Marine by Ummang Harmony Lifestyles LLP is an 88-unit SRA-sanctioned project in Juhu, Mumbai 400049, launched in December 2025 with possession due in June 2030. 53 units booked out of 56 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
45th Marine is an SRA-sanctioned project by Ummang Harmony Lifestyles LLP in Juhu, Mumbai 400049, registered with MahaRERA as PM1180002501900. It was launched in December 2025. It has 88 units in 1 building: 81 homes (1 RK, 2 BHK, 3 BHK and 4 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 88 units, 56 are for sale and 32 are rehab units for existing members.
Its registered possession date is June 2030, unchanged since launch. Construction: excavation 45% complete, structure (RCC) not started, final finishes not started.
53 units booked out of 56 units for sale (95%).