Azure Residences, Versova

by Soar High Infracon LLP · Versova, Mumbai 400061 · Map

Launched
Dec 20254 yrs 4 mths promised
Possession (MahaRERA)
Apr 2030Not extended
Concrete structure
0%Early stage
Booked
39 of 7353% · 26 in Jul 2026
Buildings
10.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
34
3 BHK
28
4 BHK
3
Other units
8
Total units
73
Buildings
1
Land
0.7 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation65%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 5%Oct 2026: Excavation 65%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 65%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
65%0%0%39
5%0%0%26
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400061

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400061
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 4 mths5 yrs 4 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Apr 2030Jun 2031
Concrete structure (RCC)0%0%
Units booked53%49%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Azure Residences by Soar High Infracon LLP is a 73-unit SRA-sanctioned project in Versova, Mumbai 400061, launched in December 2025 with possession due in April 2030. 39 units booked out of total 73 units. Work on the concrete structure (RCC) has not started.

Read full summary

Azure Residences is an SRA-sanctioned project by Soar High Infracon LLP in Versova, Mumbai 400061, registered with MahaRERA as PM1180002501960. It was launched in December 2025. It has 73 units in 1 building: 65 homes (2, 3 and 4 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2030, unchanged since launch. Construction: excavation 65% complete, structure (RCC) not started, final finishes not started.

39 units booked out of total 73 units (53%). Since the July 2026 update, 13 more units have been booked.