Sankirt Jasmine, Andheri East
by Sankirt Realtors LLP · Andheri East, Mumbai 400069 · Map
- Launched
- Feb 20263 yrs 1 mth promised
- Possession (MahaRERA)
- Mar 2029Not extended
- Concrete structure
- 51%Mid-construction
- Booked (free sale)
- 89 of 89100% · 127 rehab units
- Buildings
- 20.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale89 booked out of 89 units
Rehab127 units for existing members
Total 216 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 130
- 2 BHK
- 50
- Other units
- 36
- Total units
- 216
- Buildings
- 2
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 89
- Rehab units
- 127
- Reserved units
- 6
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 51% | 0% | 89 | |
| 100% | 7% | 0% | 6 |
"–" means MahaRERA shows no figure for that update.
About this project
Sankirt Jasmine by Sankirt Realtors LLP is a 216-unit SRA-sanctioned project in Andheri East, Mumbai 400069, launched in February 2026 with possession due in March 2029. 89 units booked out of 89 units for sale. The concrete structure (RCC) is 51% complete.
Read full summary
Sankirt Jasmine is an SRA-sanctioned project by Sankirt Realtors LLP in Andheri East, Mumbai 400069, registered with MahaRERA as PM1180002502396. It was launched in February 2026. It has 216 units in 2 buildings: 180 homes (1 and 2 BHK) and 36 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 216 units, 89 are for sale and 127 are rehab units for existing members.
Its registered possession date is March 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 51% complete, final finishes not started.
89 units booked out of 89 units for sale (100%). Since the July 2026 update, 83 more units have been booked and the reported concrete structure (RCC) has gone from 7% to 51%.