Gurukrupa Maurya, Andheri West
by Gurukrupa Realcon Buildtech LLP · Andheri West, Mumbai 400053 · Map
- Launched
- Mar 20263 yrs promised
- Possession (MahaRERA)
- Mar 2029Not extended
- Concrete structure
- 0%Early stage
- Booked
- 0 of 10%
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 1
- Total units
- 1
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 0 | |
| 65% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Gurukrupa Maurya by Gurukrupa Realcon Buildtech LLP is a 1-unit BMC-sanctioned project in Andheri West, Mumbai 400053, launched in March 2026 with possession due in March 2029. 0 units booked out of total 1 unit. Work on the concrete structure (RCC) has not started.
Read full summary
Gurukrupa Maurya is a BMC-sanctioned project by Gurukrupa Realcon Buildtech LLP in Andheri West, Mumbai 400053, registered with MahaRERA as PM1180002502536. It was launched in March 2026. It has 1 unit in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is March 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.
0 units booked out of total 1 unit (0%).
Gurukrupa Realcon's track record in Mumbai
MahaRERA projects registered 2019–2026 in Mumbai
| Projects registered with MahaRERA | 25 |
|---|---|
| Total units across these projects | 2,757 |
| Completed without extending the possession date | 10 |
| Completed after an extension | 2 |
| Lapsed | 3 |
| Under construction | 10 |
| Possession date extended on the builder's application | 2 |
| Typical time from launch to 100% structure | 2 years 9 months |
| MahaRERA complaints (filed by or against the builder), all Gurukrupa Realcon projects | 3 (3 of 25 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.