Kripa Oasis, Khar West

by Kripa Oneness Pvt Ltd · Khar West, Mumbai 400052 · Map

Launched
Mar 20262 yrs 3 mths promised
Possession (MahaRERA)
Jun 2028Not extended
Concrete structure
95%Mid-construction
Booked (free sale)
0 of 10% · 2 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 1 unit

Rehab2 units for existing members

Total 3 units. Rehab units are not for sale.

Project facts

3 BHK
2
Other units
1
Total units
3
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
1
Rehab units
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)95%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 100%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 30%Oct 2026: Concrete structure (RCC) 95%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 95%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%95%0%0
100%30%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Kripa Oasis by Kripa Oneness Pvt Ltd is a 3-unit BMC-sanctioned project in Khar West, Mumbai 400052, launched in March 2026 with possession due in June 2028. 0 units booked out of 1 unit for sale. The concrete structure (RCC) is 95% complete.

Read full summary

Kripa Oasis is a BMC-sanctioned project by Kripa Oneness Pvt Ltd in Khar West, Mumbai 400052, registered with MahaRERA as PM1180002502588. It was launched in March 2026. It has 3 units in 1 building: 2 homes (3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 3 units, 1 is for sale and 2 are rehab units for existing members.

Its registered possession date is June 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 95% complete, final finishes not started.

0 units booked out of 1 unit for sale (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 30% to 95%.