Skip to main content

Dps Vista, Borivali East

by Bp Infra Buildcon LLP · Borivali East, Mumbai 400066 · Map

Launched
Mar 20262 yrs 9 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
0%Early stage
Booked
–
Buildings
10.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Total units
–
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 50%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%–
50%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Dps Vista by Bp Infra Buildcon LLP is a BMC-sanctioned project in Borivali East, Mumbai 400066, launched in March 2026 with possession due in December 2028. Work on the concrete structure (RCC) has not started.

Read full summary

Dps Vista is a BMC-sanctioned project by Bp Infra Buildcon LLP in Borivali East, Mumbai 400066, registered with MahaRERA as PM1180002502653. It was launched in March 2026. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.