Nasam Chambers, Bandra East

by Nasam Homes · Bandra East, Mumbai 400051 · Map

Launched
Mar 20263 yrs promised
Possession (MahaRERA)
Mar 2029Not extended
Concrete structure
0%Early stage
Booked
30 of 6844% · 0 in Jul 2026
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
68
Total units
68
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 0%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%30
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Nasam Chambers by Nasam Homes is a 68-unit SRA-sanctioned project in Bandra East, Mumbai 400051, launched in March 2026 with possession due in March 2029. 30 units booked out of total 68 units. Work on the concrete structure (RCC) has not started.

Read full summary

Nasam Chambers is an SRA-sanctioned project by Nasam Homes in Bandra East, Mumbai 400051, registered with MahaRERA as PM1180002502954. It was launched in March 2026. It has 68 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

30 units booked out of total 68 units (44%). Since the July 2026 update, 30 more units have been booked.