by Vinayak Gurudatta Developers · Goregaon West, Mumbai 400104 · Map

Launched
Mar 20263 yrs 9 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
14 of 2850% · 25 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale14 booked out of 28 units

Rehab25 units for existing members

Total 53 units. Rehab units are not for sale.

Project facts

1 RK
13
2 BHK
26
Other units
14
Total units
53
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
28
Rehab units
25
Reserved units
13

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation80%
Concrete structure (slabs)0%
Finishes, lifts and services4%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 75%Oct 2026: Excavation 80%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 2%Oct 2026: Final finishes 4%Excavation 80%Final finishes 4%Concrete structure (RCC) 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
80%0%4%14
75%0%2%13

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400104

Projects with 10–80 flats, launched within 1 year of this one.

Compared with 5 similar projects in PIN 400104
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 9 mths2 yrs 11 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)Dec 2029Aug 2029
Concrete structure (RCC)0%0%
Units booked (free sale)50%0%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Shivay by Vinayak Gurudatta Developers is a 53-unit BMC-sanctioned project in Goregaon West, Mumbai 400104, launched in March 2026 with possession due in December 2029. 14 units booked out of 28 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Shivay is a BMC-sanctioned project by Vinayak Gurudatta Developers in Goregaon West, Mumbai 400104, registered with MahaRERA as PM1180002503002. It was launched in March 2026. It has 53 units in 1 building: 39 homes (1 RK and 2 BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 53 units, 28 are for sale and 25 are rehab units for existing members.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation 80% complete, structure (RCC) not started, final finishes 4% complete.

14 units booked out of 28 units for sale (50%). Since the July 2026 update, 1 more unit has been booked.