Sheetal Uptown Phase II, Kandivali East
by Sidheshwar Lifespaces Private Limited · Kandivali East, Mumbai 400101 · Map
- Launched
- Mar 20264 yrs 9 mths promised
- Possession (MahaRERA)
- Dec 2030Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 0 of 680% · 395 rehab units
- Buildings
- 31.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 68 units
Rehab395 units for existing members
Total 463 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 439
- Other units
- 24
- Total units
- 463
- Buildings
- 3
- Land
- 1.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 68
- Rehab units
- 395
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 53% | 0% | 0% | 0 | |
| 53% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Sheetal Uptown Phase II by Sidheshwar Lifespaces Private Limited is a 463-unit SRA-sanctioned project in Kandivali East, Mumbai 400101, launched in March 2026 with possession due in December 2030. 0 units booked out of 68 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Sheetal Uptown Phase II is an SRA-sanctioned project by Sidheshwar Lifespaces Private Limited in Kandivali East, Mumbai 400101, registered with MahaRERA as PM1180002503023. It was launched in March 2026. It has 463 units in 3 buildings: 439 homes (1 BHK) and 24 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 463 units, 68 are for sale and 395 are rehab units for existing members.
Its registered possession date is December 2030, unchanged since launch. Construction: excavation 53% complete, structure (RCC) not started, final finishes not started.
0 units booked out of 68 units for sale (0%).