Shiv Aashray, Andheri East

by Shiva Rameehans Constructions LLP · Andheri East, Mumbai 400099 · Map

Launched
Apr 20261 yr 9 mths promised
Possession (MahaRERA)
Jan 2028Not extended
Concrete structure
0%Early stage
Booked (free sale)
7 of 1741% · 14 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale7 booked out of 17 units

Rehab14 units for existing members

Total 31 units. Rehab units are not for sale.

Project facts

1 BHK
16
2 BHK
2
3 BHK
10
Other units
3
Total units
31
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
17
Rehab units
14
Reserved units
7

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services20%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 50%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 20%Excavation 100%Final finishes 20%Concrete structure (RCC) 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%20%7
50%0%0%7

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400099

Projects with 10–60 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400099
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 9 mths2 yrs 7 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Jan 2028Jun 2028
Concrete structure (RCC)0%0%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Shiv Aashray by Shiva Rameehans Constructions LLP is a 31-unit BMC-sanctioned project in Andheri East, Mumbai 400099, launched in April 2026 with possession due in January 2028. 7 units booked out of 17 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Shiv Aashray is a BMC-sanctioned project by Shiva Rameehans Constructions LLP in Andheri East, Mumbai 400099, registered with MahaRERA as PM1180002600079. It was launched in April 2026. It has 31 units in 1 building: 28 homes (1, 2 and 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 31 units, 17 are for sale and 14 are rehab units for existing members.

Its registered possession date is January 2028, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes 20% complete.

7 units booked out of 17 units for sale (41%).