by Poonam Developers LLP · Andheri West, Mumbai 400053 · Map
- Launched
- May 20265 yrs 1 mth promised
- Possession (MahaRERA)
- Jun 2031Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 5 of 1242% · 4 rehab units
- Buildings
- 20.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale5 booked out of 12 units
Rehab4 units for existing members
Land-owner share2 units, not for sale
Total 18 units. Rehab and land-owner units are not for sale.
Project facts
- 1 BHK
- 2
- 2 BHK
- 2
- 3 BHK
- 2
- Other units
- 12
- Total units
- 18
- Buildings
- 2
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 12
- Rehab units
- 4
- Land-owner share (not for sale)
- 2
- Reserved units
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Work not started as of Oct 2026
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | 5 | |
| 0% | 0% | 0% | 2 |
"–" means MahaRERA shows no figure for that update.
About this project
Polaris by Poonam Developers LLP is an 18-unit BMC-sanctioned project in Andheri West, Mumbai 400053, launched in May 2026 with possession due in June 2031. 5 units booked out of 12 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Polaris is a BMC-sanctioned project by Poonam Developers LLP in Andheri West, Mumbai 400053, registered with MahaRERA as PM1180002600366. It was launched in May 2026. It has 18 units in 2 buildings: 6 homes (1, 2 and 3 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 18 units, 12 are for sale, 4 are rehab units for existing members and 2 are the land-owner's share, not for sale.
Its registered possession date is June 2031, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.
5 units booked out of 12 units for sale (42%). Since the July 2026 update, 3 more units have been booked.