Shenoy Apartments Chsl, Borivali West

by Namo Shreen Ventures LLP · Borivali West, Mumbai 400103 · Map

Launched
May 20264 yrs 7 mths promised
Possession (MahaRERA)
Dec 2030Not extended
Concrete structure
0%Early stage
Booked (free sale)
2 of 1118% · 20 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale2 booked out of 11 units

Rehab20 units for existing members

Total 31 units. Rehab units are not for sale.

Project facts

1 BHK
9
2 BHK
13
3 BHK
2
Other units
7
Total units
31
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
11
Rehab units
20
Reserved units
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 0%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%2
0%0%0%2

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400103

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400103
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 7 mths3 yrs
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2030Mar 2029
Concrete structure (RCC)0%0%
Units booked (free sale)18%4%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Shenoy Apartments Chsl by Namo Shreen Ventures LLP is a 31-unit BMC-sanctioned project in Borivali West, Mumbai 400103, launched in May 2026 with possession due in December 2030. 2 units booked out of 11 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Shenoy Apartments Chsl is a BMC-sanctioned project by Namo Shreen Ventures LLP in Borivali West, Mumbai 400103, registered with MahaRERA as PM1180002600506. It was launched in May 2026. It has 31 units in 1 building: 24 homes (1, 2 and 3 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 31 units, 11 are for sale and 20 are rehab units for existing members.

Its registered possession date is December 2030, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

2 units booked out of 11 units for sale (18%).