Charkop (1) Satkar Coop Hsg Soc Ltd, Kandivali West

by Sandhya & Kotecha Developers · Kandivali West, Mumbai 400067 · Map

Launched
Jun 20264 yrs 6 mths promised
Possession (MahaRERA)
Dec 2030Not extended
Concrete structure
0%Early stage
Booked (free sale)
0 of 100% · 22 rehab units
Buildings
20.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 10 units

Rehab22 units for existing members

Total 32 units. Rehab units are not for sale.

Project facts

1 BHK
2
2 BHK
17
3 BHK
13
Total units
32
Buildings
2
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
10
Rehab units
22

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation95%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 95%Oct 2026: Excavation 95%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 95%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
95%0%0%0
95%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400067

Projects with 10–70 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 6 mths3 yrs 5 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Dec 2030Mar 2030
Concrete structure (RCC)0%0%
Units booked (free sale)0%0%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Charkop (1) Satkar Coop Hsg Soc Ltd by Sandhya & Kotecha Developers is a 32-unit MHADA-sanctioned project in Kandivali West, Mumbai 400067, launched in June 2026 with possession due in December 2030. 0 units booked out of 10 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Charkop (1) Satkar Coop Hsg Soc Ltd is a MHADA-sanctioned project by Sandhya & Kotecha Developers in Kandivali West, Mumbai 400067, registered with MahaRERA as PM1180002600590. It was launched in June 2026. It has 32 units in 2 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 32 units, 10 are for sale and 22 are rehab units for existing members.

Its registered possession date is December 2030, unchanged since launch. Construction: excavation 95% complete, structure (RCC) not started, final finishes not started.

0 units booked out of 10 units for sale (0%).