Starview, Chembur

by Balan Realty LLP · Chembur, Mumbai 400071 · Map

Launched
Jun 20264 yrs 6 mths promised
Possession (MahaRERA)
Dec 2030Not extended
Concrete structure
0%Early stage
Booked (free sale)
0 of 40% · 12 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 4 units

Rehab12 units for existing members

Total 16 units. Rehab units are not for sale.

Project facts

1 BHK
4
2 BHK
3
3 BHK
6
Other units
3
Total units
16
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
4
Rehab units
12

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 0%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400071

Projects with up to 30 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 6 mths3 yrs
Possession date extendedNo0 of 4
Possession date (MahaRERA)Dec 2030Jun 2029
Concrete structure (RCC)0%0%
Units booked (free sale)0%0%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Starview by Balan Realty LLP is a 16-unit BMC-sanctioned project in Chembur, Mumbai 400071, launched in June 2026 with possession due in December 2030. 0 units booked out of 4 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Starview is a BMC-sanctioned project by Balan Realty LLP in Chembur, Mumbai 400071, registered with MahaRERA as PM1180002600699. It was launched in June 2026. It has 16 units in 1 building: 13 homes (1, 2 and 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 16 units, 4 are for sale and 12 are rehab units for existing members.

Its registered possession date is December 2030, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

0 units booked out of 4 units for sale (0%).