Skip to main content

Om Abhishek Chsl, Borivali West

by Rander Niketam LLP · Borivali West, Mumbai 400091 · Map

Launched
Jun 20262 yrs promised
Possession (MahaRERA)
Jun 2028Not extended
Concrete structure
0%Early stage
Booked (free sale)
0 of 150% · 14 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 15 units

Rehab14 units for existing members

Total 29 units. Rehab units are not for sale.

Project facts

1 BHK
8
2 BHK
2
3 BHK
9
Other units
10
Total units
29
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
15
Rehab units
14

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 50%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%0
50%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Om Abhishek Chsl by Rander Niketam LLP is a 29-unit BMC-sanctioned project in Borivali West, Mumbai 400091, launched in June 2026 with possession due in June 2028. 0 units booked out of 15 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Om Abhishek Chsl is a BMC-sanctioned project by Rander Niketam LLP in Borivali West, Mumbai 400091, registered with MahaRERA as PM1180002600779. It was launched in June 2026. It has 29 units in 1 building: 19 homes (1, 2 and 3 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 29 units, 15 are for sale and 14 are rehab units for existing members.

Its registered possession date is June 2028, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

0 units booked out of 15 units for sale (0%).