Rashmi Avenue, Dahisar

by Modi's Navnirman Limited · Dahisar, Mumbai 400068 · Map

Launched
Jun 20263 yrs 2 mths promised
Possession (MahaRERA)
Aug 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
5 of 4910% · 91 rehab units
Buildings
21.1 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale5 booked out of 49 units

Rehab91 units for existing members

Total 140 units. Rehab units are not for sale.

Project facts

1 BHK
51
2 BHK
69
3 BHK
1
Other units
19
Total units
140
Buildings
2
Land
1.1 acres
Phases
1
MahaRERA complaints
1
Free-sale units
49
Rehab units
91

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation90%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 0%Oct 2026: Excavation 90%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 90%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
90%0%0%5
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400068

Projects with 60–250 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400068
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 2 mths3 yrs 6 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Aug 2029Dec 2029
Concrete structure (RCC)0%0%
Units booked (free sale)10%0%
MahaRERA complaints (filed by or against the builder)10

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Rashmi Avenue by Modi's Navnirman Limited is a 140-unit BMC-sanctioned project in Dahisar, Mumbai 400068, launched in June 2026 with possession due in August 2029. 5 units booked out of 49 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Rashmi Avenue is a BMC-sanctioned project by Modi's Navnirman Limited in Dahisar, Mumbai 400068, registered with MahaRERA as PM1180002600962. It was launched in June 2026. It has 140 units in 2 buildings: 121 homes (1, 2 and 3 BHK) and 19 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 140 units, 49 are for sale and 91 are rehab units for existing members.

Its registered possession date is August 2029, unchanged since launch. Construction: excavation 90% complete, structure (RCC) not started, final finishes not started.

5 units booked out of 49 units for sale (10%). Since the July 2026 update, 5 more units have been booked.