Prime Vista, Chembur

by Megaaplex Prime Propertes LLP · Chembur, Mumbai 400071 · Map

Launched
Jul 20264 yrs 11 mths originally promised
Possession (MahaRERA)
Oct 2031Extended by 4 mths
Concrete structure
0%Early stage
Booked
–
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Total units
–
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation95%
Concrete structure (slabs)0%
Finishes, lifts and services0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
95%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Prime Vista by Megaaplex Prime Propertes LLP is a BMC-sanctioned project in Chembur, Mumbai 400071, launched in July 2026 with possession due in October 2031. Work on the concrete structure (RCC) has not started.

Read full summary

Prime Vista is a BMC-sanctioned project by Megaaplex Prime Propertes LLP in Chembur, Mumbai 400071, registered with MahaRERA as PM1180002601286. It was launched in July 2026. Its MahaRERA status is Active.

Its registered possession date is October 2031, extended by 4 months from the original June 2031. Construction: excavation 95% complete, structure (RCC) not started, final finishes not started.