Venus Chs, Andheri East
by Skyline Landmark - II · Andheri East, Mumbai 400093 · Map
- Launched
- Oct 20262 yrs 2 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 4 of 667% · 11 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale4 booked out of 6 units
Rehab11 units for existing members
Total 17 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 5
- 2 BHK
- 8
- Other units
- 4
- Total units
- 17
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 6
- Rehab units
- 11
- Reserved units
- 4
Construction progress
As reported by the builder to MahaRERA (whole project)
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 4 |
"–" means MahaRERA shows no figure for that update.
About this project
Venus Chs by Skyline Landmark - II is a 17-unit BMC-sanctioned project in Andheri East, Mumbai 400093, launched in October 2026 with possession due in December 2028. 4 units booked out of 6 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Venus Chs is a BMC-sanctioned project by Skyline Landmark - II in Andheri East, Mumbai 400093, registered with MahaRERA as PM1180002602052. It was launched in October 2026. It has 17 units in 1 building: 13 homes (1 and 2 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 17 units, 6 are for sale and 11 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.
4 units booked out of 6 units for sale (67%).