Empire Goldcrest, Borivali West
by Empire Realty · Borivali West, Mumbai 400103 · Map
- Launched
- Oct 20264 yrs promised
- Possession (MahaRERA)
- Oct 2030Not extended
- Concrete structure
- 0%Early stage
- Booked
- –
- Buildings
- 20.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Total units
- –
- Buildings
- 2
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | – |
"–" means MahaRERA shows no figure for that update.
About this project
Empire Goldcrest by Empire Realty is a BMC-sanctioned project in Borivali West, Mumbai 400103, launched in October 2026 with possession due in October 2030. Work on the concrete structure (RCC) has not started.
Read full summary
Empire Goldcrest is a BMC-sanctioned project by Empire Realty in Borivali West, Mumbai 400103, registered with MahaRERA as PM1180002602491. It was launched in October 2026. Its MahaRERA status is Active.
Its registered possession date is October 2030, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.
Empire Realty's track record in Mumbai
MahaRERA projects registered 2022–2026 in Mumbai
| Projects registered with MahaRERA | 12 |
|---|---|
| Total units across these projects | 690 |
| Completed without extending the possession date | 6 |
| Completed after an extension | 0 |
| Lapsed | 0 |
| Under construction | 6 |
| Possession date extended on the builder's application | 0 |
| Typical time from launch to 100% structure | 2 years |
| MahaRERA complaints (filed by or against the builder), all Empire Realty projects | 0 (0 of 12 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.