Akassh Amazonia Tower 1, Vikhroli
by Heer Mehta Landmark Developers Private Limited · Vikhroli, Mumbai 400083 · Map
- Launched
- Jul 20254 yrs 11 mths promised
- Possession (MahaRERA)
- Jun 2030Not extended
- Concrete structure
- 5%Mid-construction
- Booked
- 0 of 4430%
- Buildings
- 12.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 276
- 2 BHK
- 153
- Other units
- 14
- Total units
- 443
- Buildings
- 1
- Land
- 2.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 5% | 0% | 0 | |
| 100% | 0% | 0% | 0 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Akassh Amazonia Tower 1 by Heer Mehta Landmark Developers Private Limited is a 443-unit SRA-sanctioned project in Vikhroli, Mumbai 400083, launched in July 2025 with possession due in June 2030. 0 units booked out of total 443 units. The concrete structure (RCC) is 5% complete.
Read full summary
Akassh Amazonia Tower 1 is an SRA-sanctioned project by Heer Mehta Landmark Developers Private Limited in Vikhroli, Mumbai 400083, registered with MahaRERA as PM1181012500342. It was launched in July 2025. It has 443 units in 1 building: 429 homes (1 and 2 BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is June 2030, unchanged since launch. Construction: excavation complete, structure (RCC) 5% complete, final finishes not started.
0 units booked out of total 443 units (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 5%.