Skip to main content

Mauli Pride 1 Bcde, Malad East

by Mauli Sai Developers Pvt Ltd · Malad East, Mumbai 400097 · Map

Launched
Mar 20262 yrs 9 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
17%Mid-construction
Booked
50 of 40512% · 31 in Jul 2026
Buildings
42.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
345
2 BHK
27
Other units
33
Total units
405
Buildings
4
Land
2.2 acres
Phases
1
MahaRERA complaints
0
Reserved units
27

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)17%
Finishes, lifts and services8%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 100%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 17%Oct 2026: Concrete structure (RCC) 17%Jul 2026: Final finishes 8%Oct 2026: Final finishes 8%Excavation 100%Concrete structure (RCC) 17%Final finishes 8%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%17%8%50
100%17%8%31

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Mauli Pride 1 Bcde by Mauli Sai Developers Pvt Ltd is a 405-unit SRA-sanctioned project in Malad East, Mumbai 400097, launched in March 2026 with possession due in December 2028. 50 units booked out of total 405 units. The concrete structure (RCC) is 17% complete.

Read full summary

Mauli Pride 1 Bcde is an SRA-sanctioned project by Mauli Sai Developers Pvt Ltd in Malad East, Mumbai 400097, registered with MahaRERA as PM1181012502549. It was launched in March 2026. It has 405 units in 4 buildings: 372 homes (1 and 2 BHK) and 33 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 17% complete, final finishes 8% complete.

50 units booked out of total 405 units (12%). Since the July 2026 update, 19 more units have been booked.