Aurum Endeavour, Wadala West
by Ashok Johaan Realty LLP · Wadala West, Mumbai 400031 · Map
- Launched
- Jun 20253 yrs 11 mths promised
- Possession (MahaRERA)
- May 2029Not extended
- Concrete structure
- 55%Mid-construction
- Booked (free sale)
- 21 of 3070% · 16 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale21 booked out of 30 units
Rehab16 units for existing members
Total 46 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 15
- 3 BHK
- 8
- Other units
- 23
- Total units
- 46
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 30
- Rehab units
- 16
- Reserved units
- 19
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 55% | 0% | 21 | |
| 100% | 5% | 0% | 21 | |
| 0% | 0% | 0% | 19 |
"–" means MahaRERA shows no figure for that update.
About this project
Aurum Endeavour by Ashok Johaan Realty LLP is a 46-unit BMC-sanctioned project in Wadala West, Mumbai 400031, launched in June 2025 with possession due in May 2029. 21 units booked out of 30 units for sale. The concrete structure (RCC) is 55% complete.
Read full summary
Aurum Endeavour is a BMC-sanctioned project by Ashok Johaan Realty LLP in Wadala West, Mumbai 400031, registered with MahaRERA as PR1170002500147. It was launched in June 2025. It has 46 units in 1 building: 23 homes (2 and 3 BHK) and 23 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 46 units, 30 are for sale and 16 are rehab units for existing members.
Its registered possession date is May 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 55% complete, final finishes not started.
21 units booked out of 30 units for sale (70%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 5% to 55%.