Prodigy One, Matunga
by Prodigy Realty LLP · Matunga, Mumbai 400019 · Map
- Launched
- Oct 20253 yrs 9 mths promised
- Possession (MahaRERA)
- Jul 2029Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 1 of 714% · 16 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale1 booked out of 7 units
Rehab16 units for existing members
Total 23 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 1
- 3 BHK
- 22
- Total units
- 23
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 7
- Rehab units
- 16
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 1 | |
| 100% | 0% | 0% | 0 | |
| 20% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400019
Projects with 10–50 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 9 mths | 3 yrs 2 mths |
| Possession date extended | No | 0 of 5 |
| Possession date (MahaRERA) | Jul 2029 | Mar 2029 |
| Concrete structure (RCC) | 0% | 10% |
| Units booked (free sale) | 14% | 0% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Savannah, Matunga
- Avyukta Imperial, Matunga
- Amaris Suites, Matunga
- Chheda Imperial, Matunga
- Royal Oak, Matunga
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Savannah | October 2025 | December 2029 | 0% | 0 units booked out of 12 units for sale |
| Avyukta Imperial | September 2025 | September 2028 | 0% | 0 units booked out of 10 units for sale |
| Amaris Suites | January 2026 | March 2029 | 25% | 0 units booked out of 6 units for sale |
| Chheda Imperial | June 2025 | December 2029 | 10% | 2 units booked out of 7 units for sale |
| Royal Oak | June 2025 | November 2027 | 90% | 1 unit booked out of 5 units for sale |
About this project
Prodigy One by Prodigy Realty LLP is a 23-unit BMC-sanctioned project in Matunga, Mumbai 400019, launched in October 2025 with possession due in July 2029. 1 unit booked out of 7 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Prodigy One is a BMC-sanctioned project by Prodigy Realty LLP in Matunga, Mumbai 400019, registered with MahaRERA as PR1170002501302. It was launched in October 2025. It has 23 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 23 units, 7 are for sale and 16 are rehab units for existing members.
Its registered possession date is July 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.
1 unit booked out of 7 units for sale (14%). Since the July 2026 update, 1 more unit has been booked.