Embassy Citadel, Worli
by Equinox India Infraestate Limited, Spero Properties And Services Private Limited · Worli, Mumbai 400018 · Map
- Launched
- Dec 20258 yrs 6 mths promised
- Possession (MahaRERA)
- Jun 2034Not extended
- Concrete structure
- 0%Early stage
- Booked
- 78 of 31625% · 39 in Jul 2026
- Buildings
- 211.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 3 BHK
- 48
- 4 BHK
- 244
- 5+ BHK
- 22
- Other units
- 2
- Total units
- 316
- Buildings
- 2
- Land
- 11.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 37% | 0% | 0% | 78 | |
| 8% | 0% | 0% | 39 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Embassy Citadel by Equinox India Infraestate Limited, Spero Properties And Services Private Limited is a 316-unit BMC-sanctioned project in Worli, Mumbai 400018, launched in December 2025 with possession due in June 2034. 78 units booked out of total 316 units. Work on the concrete structure (RCC) has not started.
Read full summary
Embassy Citadel is a BMC-sanctioned project by Equinox India Infraestate Limited, Spero Properties And Services Private Limited in Worli, Mumbai 400018, registered with MahaRERA as PR1170002501931. It was launched in December 2025. It has 316 units in 2 buildings: 314 homes (3, 4 and 5+ BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is June 2034, unchanged since launch. Construction: excavation 37% complete, structure (RCC) not started, final finishes not started.
78 units booked out of total 316 units (25%). Since the July 2026 update, 39 more units have been booked.