An-Nur Residency, Mumbai Central
by Wiz Builders And Developers LLP · Mumbai Central, Mumbai 400008 · Map
- Launched
- Mar 20263 yrs 9 mths originally promised
- Possession (MahaRERA)
- Apr 2032Extended by 2 yrs 4 mths
- Concrete structure
- 50%Mid-construction
- Booked (free sale)
- 0 of 800% · 71 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 80 units
Rehab71 units for existing members
Total 151 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 127
- 2 BHK
- 2
- Other units
- 22
- Total units
- 151
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 80
- Rehab units
- 71
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 50% | 0% | 0 | |
| 100% | 10% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
An-Nur Residency by Wiz Builders And Developers LLP is a 151-unit BMC-sanctioned project in Mumbai Central, Mumbai 400008, launched in March 2026 with possession due in April 2032. 0 units booked out of 80 units for sale. The concrete structure (RCC) is 50% complete.
Read full summary
An-Nur Residency is a BMC-sanctioned project by Wiz Builders And Developers LLP in Mumbai Central, Mumbai 400008, registered with MahaRERA as PR1170002502720. It was launched in March 2026. It has 151 units in 1 building: 129 homes (1 and 2 BHK) and 22 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 151 units, 80 are for sale and 71 are rehab units for existing members.
Its registered possession date is April 2032, extended by 2 years 4 months from the original December 2029. Construction: excavation complete, structure (RCC) 50% complete, final finishes not started.
0 units booked out of 80 units for sale (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 10% to 50% and the possession date has moved from December 2029 to April 2032.